California Oak Foundation v. Regents of the University of California (Sept. 3, 2010) No. A122511, available at CourtWebsite.

The California Oak Foundation and others filed petitions challenging the Regents of the University of California’s certification of an EIR and approval of a project for building athletic facilities at the Berkeley campus. The Oak Foundation alleged that the EIR was inadequate under CEQA in its (1) description of baseline conditions; (2) project description; (3) statement of objectives; (4) discussion of alternatives; and (5) discussion of biological and archaeological impacts. It also alleged improper (1) delegating of authority to certify the EIR to the Regents’ Committee on Grounds and Buildings; (2) giving approval to the project before certifying the EIR; (3) failing to recirculate the Draft EIR; and (4) making findings and a statement of overriding considerations without evidentiary support. The court rejected all of these arguments.

First, the court found that the EIR accurately described the existing baseline conditions, and the geotechnical study made available after DEIR circulation adequately matched up with that baseline. Release of the study after circulation also did not require recirculation because it did not constitute significant new information and merely confirmed information already stated. The court held that omitting discussion of the California Geological Survey and United States Geological Survey comment letters was of no consequence because they did not show that the conclusions in the geology report were erroneous.

The court found the project’s description complied with CEQA Guidelines, section 15124. Evidence supported the degree of specificity used. The methodology for presenting and analyzing project alternatives in matrix and narrative format was appropriate despite some broad wording. The significant environmental impacts and corresponding components of each of the alternatives were evaluated against the corresponding component of the project, thus demonstrating a good faith effort to provide a meaningful discussion of a range of reasonable project alternatives, which according to the court was all that CEQA requires. Finally, substantial evidence supported the Regents’ conclusions on archeological and biological resources, their findings, and the statement of overriding considerations.

The court held that the Committee on Grounds and Buildings appropriately certified the EIR based on its approval authority over the project. Further, the project was not approved before certifying the EIR because the Regents’ policy related to its earlier approval of funding did not constitute project approval until completion of the project’s design review.

Therefore, the court affirmed the denial of the California Oak Foundation’s petition for writ of mandate and upheld the EIR certification and project approval.